Our HFJI project in 10 steps

1 000 000.00 Needed Donation

STEP 1

Health Master Plans

  • Project definition and goals set-up
  • Stakeholders identification and governance definition
  • Medical, technical, logistics and capacity programs
  • Assumptions for clinical activities and medico-technical efficiency
  • Human resources program
  • Preliminary list of equipment

STEP 2

Feasibility Studies and Technical Proposals

  • Medical strategy, stakes and goals
  • Functional requirements and main circulation principles
  • Site’s constraints
  • Technical program
  • Infrastructure Pre programming
  • Surface Areas by Functional Unit
  • Functional Architectural Orientations
  • Technical specifications
  • Rooms datasheets
  • Budget assessment

STEP 3

Financial Engineering

  • Construction cost assessment
  • Equipment cost assessment
  • Revenue and operating costs assessment
  • Business Plan
  • Business model

STEP 4

Building and Civil Works International

  • Architectural and engineering studies
  • Main technical principles
  • Project Management
  • Technical selection
  • High level drawings
  • Security (fire, radioprotection…)
  • Administratives licences
  • Detailed drawings for each subcontractor
  • Detailed technical requirements
  • Construction
  • Contracting
  • Execution
  • Tests
  • Security committee

STEP 5

Equipment and Logistics

  • Preliminary list of equipment
  • Technical specifications
  • Technical requirements
  • Pre-installation drawings
  • Tenders
  • Negotiations and purchasing
  • Pre-installation works
  • Orders
  • Shipment
  • Customs clearance
  • Delivery on site
  • Inspection and Quality controls

STEP 6

Installation and Commissioning

  • Equipment dispatching
  • Installations
  • Configurations
  • Interoperability
  • Tests
  • Commissioning
  • Documentation
  • End users’ training

STEP 7

Technical Training

  • Bio-medical department organisation
  • Technicians and engineers’ training
  • Set up of an equipment management system
  • Processes
  • Documentation

STEP 8

Maintenance and Warranty

  • Building maintenance and facility management
  • Preventive and curative maintenance of equipment
  • Service contracts management

STEP 9

Human Resources and Procedures

  • Protocoles definition and working processes
  • Organisation set up
  • Jobs description
  • Hiring and staffing integration
  • Working environment
  • Training plan for medical, paramedical and technical staff
  • Training
  • Quality management by staff
  • Certification

STEP 10

Operations and Management

  • Operations and management
  • Quality processes implementation and follow-up
  • Audits
  • Skills assessment
  • Skills improvement plan
  • Key performance indicators